"We are excited to announce the official opening of commercial operations of Block B of the MBR Phase V project 17 days ahead of schedule," said Qiu Minghua, Vice General Manager of Shanghai Electric, at the ceremony. "Our company expects to complete the subsequent handover, as well as getting underway the construction of Block C, in due course."

본고는 자료 제공사에서 제공한 것으로, 연합뉴스는 내용에 대해 어떠한 편집도 하지 않았음을 밝혀 드립니다.

글자크기 설정 파란원을 좌우로 움직이시면 글자크기가 변경 됩니다.

이 글자크기로 변경됩니다.

(예시) 가장 빠른 뉴스가 있고 다양한 정보, 쌍방향 소통이 숨쉬는 다음뉴스를 만나보세요. 다음뉴스는 국내외 주요이슈와 실시간 속보, 문화생활 및 다양한 분야의 뉴스를 입체적으로 전달하고 있습니다.

(PRNewsfoto/Shanghai Electric)

in Dubai 17 Days Ahead of Schedule

(SHANGHAI, Oct. 11, 2022 PRNewswire=연합뉴스) The opening ceremony for commercial operations of Block B in phase five at Shanghai Electric's Mohammed bin Rashid Al Maktoum Solar Park (MBR Phase V) facility in Dubai was held at the site on October 10. The equipment started producing electricity for commercial use 17 days earlier than expected, marking another milestone in the construction of the Shanghai Electric facility.

"We are excited to announce the official opening of commercial operations of Block B of the MBR Phase V project 17 days ahead of schedule," said Qiu Minghua, Vice General Manager of Shanghai Electric, at the ceremony. "Our company expects to complete the subsequent handover, as well as getting underway the construction of Block C, in due course."

In addition, Omar Al-Hassan, the CEO of Shuaa Energy 3, the company in charge of implementation of the project, also expressed his appreciation and gratitude to all parties involved for their hard work and construction achievements at the opening ceremony.

Earlier in the project, its construction had been negatively affected by the pandemic, with issues such as the increase in the prices of raw materials, labor and transportation, and the inability to ship photovoltaic (PV) modules to the site on schedule. To deal with these obstacles, a crisis team composed of business professionals was assembled to resolve the issues with all parties involved. After several rounds of discussions, Shanghai Electric and the relevant parties reached an agreement, paving the way for the project to get back on track and not only meet but also beat the agreed upon completion date.

In July 2022, the shipments of some batches of modules were again delayed. In response, a team was mobilized to speed up operations. Because of the team's efforts around the clock, any time lost in the project was caught up over the course of a few weeks. After 13-days of reliability and performance tests, the equipment in Block B was approved by the local power grid operator and officially put into commercial operation 17 days ahead of schedule, marking another important milestone achieved by the MBR Phase V project.

The project is divided into three blocks - A, B and C, each with a capacity of 300 MW. Block A was put into full operation in July 2021. The design for Block C has been provisionally completed, meaning that preparations for its construction, including equipment deliveries, and the laying of underground cables, are in full swing.

Those in charge of implementing the project said that they will continue to do whatever is necessary to overcome the challenges that were faced in implementing Block B, such as those caused by the effects of the pandemic, including staff issues, so that the commissioning and commencement of commercial operations of Block C can occur as soon as possible.

About Shanghai Electric

Shanghai Electric Group Company Limited (SEHK: 2727, SSE: 601727) is a world-class high-end equipment manufacturer, focusing on smart energy, intelligent manufacturing and smart infrastructure to provide green and intelligent industrial-grade system solutions. It has a global presence in industries such as new energy, efficient clean energy, industrial automation, medical devices, and environmental protection.

Logo - https://mma.prnewswire.com/media/1800747/logo_new_Logo.jpg

(PRNewsfoto/Shanghai Electric)

Source: Shanghai Electric

[편집자 주] 본고는 자료 제공사에서 제공한 것으로, 연합뉴스는 내용에 대해 어떠한 편집도 하지 않았음을 밝혀 드립니다.

(끝)

출처 : PRNewswire 보도자료

Copyright © 연합뉴스 보도자료. 무단전재 및 재배포 금지.

이 기사에 대해 어떻게 생각하시나요?