Seoul to take down 59-year-old Seosomun Overpass next month

Lee Si-jin 2025. 7. 29. 13:57
음성재생 설정 이동 통신망에서 음성 재생 시 데이터 요금이 발생할 수 있습니다. 글자 수 10,000자 초과 시 일부만 음성으로 제공합니다.
글자크기 설정 파란원을 좌우로 움직이시면 글자크기가 변경 됩니다.

이 글자크기로 변경됩니다.

(예시) 가장 빠른 뉴스가 있고 다양한 정보, 쌍방향 소통이 숨쉬는 다음뉴스를 만나보세요. 다음뉴스는 국내외 주요이슈와 실시간 속보, 문화생활 및 다양한 분야의 뉴스를 입체적으로 전달하고 있습니다.

Vehicles pass over the Seosomun Overpass in Jung-gu, central Seoul, Tuesday. (Yonhap)

The Seosomun Overpass, once a driveway passing through the heart of Seoul, is slated for demolition over safety concerns.

The Seoul Metropolitan Government announced Tuesday that it is scheduled to remove the flyover, located in Seodaemun-gu, Seoul, by gradually closing its roads starting from Aug. 17.

According to the city government, one lane of the overpass connecting the City Hall and Chungjeongno Station of Line No. 2 will initially be closed. The opposite lane westward will subsequently be closed a week later on Aug. 24.

The overpass will be completely shut down on Sept. 21.

The city government added that construction of a new overpass will begin immediately after the original is demolished. The construction is scheduled to kick off in May 2026 and is expected to take approximately 20 months.

The 335-meter-long and 14.9-meter-wide road was used by more than 40,000 vehicles daily.

The city government determined that flyover demolition was necessary as maintenance efforts were no longer effective and public safety could not be guaranteed.

The Seosomun Overpass had multiple issues over the years, including concrete spalling and rebar corrosion in 2019, floor slab spalling in 2021, and concrete and reinforcing wire damage in the beams in 2024, due to overall concrete strength degradation.

This photo shows a concrete beam spalling found by the Seoul Metropolitan Government in November, 2024. (Seoul Metropolitan Government)

“The city has continuously worked on safety management by installing concrete falling prevention nets, repairing piers and restricting heavy vehicle traffic. But we determined that simple reinforcement measures were insufficient. Thus, the decision was made to take down the overpass,” the city government official said in a press release Tuesday.

With an estimated 10-month demolition period, the Seoul Metropolitan Government expects to complete the demolition process by May next year.

The city government asked for the public’s understanding as the traffic lanes are reduced from August to September.

Though the new bus routes have not been decided, the city government is attempting to turn 20 Incheon and Gyeonggi Province-based buses back before entering the city’s central area. And 23 Seoul buses are set to take a detour by driving toward nearby roads like Chungjeong-ro and Tongil-ro.

Drivers are asked to avoid using Seosomun-ro — the ground-level road beneath Seosomun Overpass — and take other routes, such as Sajik-ro, Saemunan-ro or Saejong-daero, as the street is expected to be congested with heavy traffic due to the reduced lanes.

Notifications will be made via the official website of the Seoul Metropolitan Government, on-site banners, posters, electronic traffic signs and social media channels.

Online guidance will also be provided through navigation systems and traffic applications.

Copyright © 코리아헤럴드. 무단전재 및 재배포 금지.